Australasian Society for Trenchless Technology
Library
Corporate membersNewsEvents
ASTT

Library

Browse the libraryTechniques A–ZAsk ASTTCorporate membersNewsEvents

ASTT

About ASTTCouncilMembershipStrategic PlanFAQContact
ASTT — Australasian Society for Trenchless Technology

The Australasian Society for Trenchless Technology — the peak industry body for trenchless engineering across Australia and New Zealand.

Regional affiliate of the ISTT

PO Box 2242, Malaga LPO WA 6944, Australia

+61 (0) 419 918 449

secretary@astt.com.au

Explore

  • Knowledge library
  • Ask ASTT
  • Corporate members
  • News
  • Events

ASTT

  • About
  • Council
  • Contact
  • Help
  • ISTT
  • Cookie preferences
© 2026 Australasian Society for Trenchless TechnologyDeveloped byEventMagix
  1. Home
  2. /Knowledge library
  3. /Snowy 2.0 – Marica Road West HDD: Engineering Innovation in Extreme Terrain
Library
MembersPaper2025

Snowy 2.0 – Marica Road West HDD: Engineering Innovation in Extreme Terrain

Rowena Stockton, Bryce Morrow

Abstract

The Marica Road West Horizontal Directional Drilling (HDD) project is a critical component of the Snowy 2.0 renewable energy initiative in Kosciuszko National Park, New South Wales, Australia. The project involved the design, drilling, installation and securing of three separate 2,240 metre long, 340 millimetre diameter threaded steel casings via HDD for power, water, and communications. The Marica Road West HDD is notable for its technical complexity, primarily due to the environmentally sensitive escarpment, with a 563 metre elevation change between the two sites, making it one of the most challenging HDD projects completed in Australia. This extreme elevation difference presented significant engineering challenges, including managing borehole fluid, ensuring borehole stability across variable geological formations and controlling high groundwater inflows. To overcome these challenges, Michels implemented innovative techniques, including a dual-rig intersect method which was essential to operate within allowable drill string parameters and the deployment of a custom-built rotary diverter for effective borehole fluid management. The project was executed within the environmentally sensitive Kosciuszko National Park, necessitating strict environmental controls with constructing a substantive groundwater containment system to prevent ground disturbance, and ecosystem impact. The successful completion of the Marica Road West HDD demonstrates significant advancements in HDD capabilities, particularly in managing extreme elevation differences and complex geological conditions within highly sensitive environmental areas. These findings are important to the trenchless industry as they provide valuable insights and methodologies for advancing challenging projects. No-Dig Down Under 2025 SNOWY 2.0 – MARICA ROAD WEST HDD: ENGINEERING INNOVATION IN EXTREME TERRAIN Rowena Stockton and Bryce Morrow 1

Full paper available to ASTT members

The abstract above is open to everyone. Sign in with your ASTT membership email to open the full PDF.

Sign inAbout membership

Techniques

Horizontal Directional Drilling (HDD)

Citation

Rowena Stockton, Bryce Morrow (2025). Snowy 2.0 – Marica Road West HDD: Engineering Innovation in Extreme Terrain. Paper presented at No-Dig Down Under 2025. ASTT Knowledge Library.

Details

Source:
No-Dig Down Under 2025
Pages:
8
File:
PDF, 1.0 MB

One-page brief

Member companies

Corporate members delivering Horizontal Directional Drilling (HDD)

Michels Trenchless Pty. Ltd.Horizontal directional drilling (HDD) is an established trenchless utility line installation technique. We have become a world leader in HDD by designing, building and mastering the use of powerful rigs to place utility lines substantially deeper than conventional trench construction, providing signWCWaipa Civil3 waters trenchless and open cut 3 waters.Utilities InfrastructureDirectional Drilling Pipe Ramming Hydro Excavation Pipe bursting PE Welding
See all 64 members delivering Horizontal Directional Drilling (HDD) →