Australasian Society for Trenchless Technology
Library
Corporate membersNewsEvents
ASTT

Library

Browse the libraryTechniques A–ZAsk ASTTCorporate membersNewsEvents

ASTT

About ASTTCouncilMembershipStrategic PlanFAQContact
ASTT — Australasian Society for Trenchless Technology

The Australasian Society for Trenchless Technology — the peak industry body for trenchless engineering across Australia and New Zealand.

Regional affiliate of the ISTT

PO Box 2242, Malaga LPO WA 6944, Australia

+61 (0) 419 918 449

secretary@astt.com.au

Explore

  • Knowledge library
  • Ask ASTT
  • Corporate members
  • News
  • Events

ASTT

  • About
  • Council
  • Contact
  • Help
  • ISTT
  • Cookie preferences
© 2026 Australasian Society for Trenchless TechnologyDeveloped byEventMagix
  1. Home
  2. /Knowledge library
  3. /Curved Microtunnelling on the Ship Canal Water Quality Project
Library
MembersPaper2019

Curved Microtunnelling on the Ship Canal Water Quality Project

Shannon Goff, Jeremy Johnson, Alan Lord

Abstract

This paper presents the design of a curved microtunnel for the Ship Canal Water Quality Project, including challenges encountered during design. This is a joint project being constructed by Seattle Public Utilities and the King County Department of Natural Resources Wastewater Treatment Division to meet federal Environmental Protection Agency Consent Decrees to limit combined sewer overflow discharges by 2025. The project will control combined wastewater and stormwater overflows from seven combined sewer basins in Seattle, Washington by storing excess flows from the affected basins. The major project elements include a 110,000 m3 storage tunnel, a 0.5 m3/s effluent pump station, five drop structures along the alignment, ancillary facilities at the five project sites to support operation of the tunnel, and conveyance pipelines and facilities to convey combined sewage to the tunnel. As the storage tunnel is located along the north side of the Lake Washington Ship Canal, the project also includes a microtunnel under the Ship Canal to convey flows from one basin on the south side. The preliminary design for the microtunnel includes two straight drives between three shafts to route the microtunnel around an existing deep utility tunnel. To avoid the need for the intermediate shaft, a curved alignment was adopted during detailed design. The 200-metre radius curve will be built in a single, 220-metre-long drive. Detailed design of the project’s tunnel, microtunnel, and pump station elements commenced in 2015. The project was issued for bid in early 2019, with construction commencement anticipated in late 2019.

Full paper available to ASTT members

The abstract above is open to everyone. Sign in with your ASTT membership email to open the full PDF.

Sign inAbout membership

Techniques

Pipe Jacking / Microtunnelling

Citation

Shannon Goff, Jeremy Johnson, Alan Lord (2019). Curved Microtunnelling on the Ship Canal Water Quality Project. Paper presented at No-Dig Down Under 2019. ASTT Knowledge Library.

Sector

water

Details

Source:
No-Dig Down Under 2019
Pages:
10
File:
PDF, 1.2 MB

One-page brief

Member companies

Corporate members delivering Pipe Jacking / Microtunnelling

WCWitt ConsultingTunnel design and rehabilitation specialistsWNZWSP New Zealand LtdFrom mountains to sea, our water experts design innovative solutions and train our industry to deliver sustainable solutions and enhance the health of water across New Zealand.Utilities InfrastructureDirectional Drilling Pipe Ramming Hydro Excavation Pipe bursting PE Welding
See all 58 members delivering Pipe Jacking / Microtunnelling →